Print
Version
BASIC COSTS OF SLUM
UPGRADING IN BRAZIL
Alex Abiko, Luiz Reynaldo de Azevedo Cardoso, Ricardo
Rinaldelli, and Heitor Cesar Riogi Haga
Slum areas in Brazil have expanded greatly,
and particularly in the last two decades.
The initiatives taken by the government in
relation to this issue have evolved from superficial actions and
measures aimed at minimizing infrastructure deficiencies to broader
interventions seeking to consolidate newly upgraded slum areas as part
of the city. This requires more far-reaching construction work and
involves at least some restructuring of the road system, relocating
and/or re-housing when necessary, and doing construction work that often
affects areas surrounding slums.
So, the aim of this
paper is to assist in planning and examining strategic concepts for
interventions in informal urban areas by compiling basic costs and
technical data associated with understanding these items.
Conclusions and recommendations are listed in relation to general
guidelines for interventions, to upgrading costs, to the data obtained
and to strategies and technologies for minimizing costs or raising the
cost-to-benefit ratio of interventions.
1. Introduction
This article is based on the project
Infrastructure Engineering in Informal Urban Areas prepared for the
World Bank by researchers at the Civil Engineering Department of the
Escola Politécnica of the University of São Paulo.
The aim is to assist in planning and
examining strategic concepts for interventions in informal urban areas
by compiling basic costs and technical data associated with
understanding these items. Although a very important aspect of these
programs, detailed analysis of costs at the design execution level does
not lie within the scope of this study.
Several slum upgrading programs and projects
in Brazil have been innovative in administrative and technological
terms, but our knowledge of the cost-related aspects of these
interventions tends to be fragmented and rather unsystematic.
A recent study analyzing slum upgrading
costs has pointed to the difficulty of obtaining reliable data on
examining costs for the Low-Income Population Sanitation Program (local
acronym PROSANEAR), which extended water supply and sewerage systems to
urban low-income populations settled in precarious situations, e.g.
slums and/or subdivisions in high-risk areas such as hillsides,
flood-prone riverside areas, etc. After painstakingly retrieving cost
data for this program, there was great variation across the eleven cases
studied and in many of them this was due to the different criteria used
for appropriating these costs (Abiko, 2003)
Major differences emerge when we compare
methods used for appropriating costs of buildings with those used for
infrastructure projects. Very little is known in relation to
infrastructure costs, even for formal sectors in cities. One reason is
that these costs involve a number of different agencies and utility
licensees using a wide range of costing methods and approaches in their
work
When there is a need to estimate the cost of
upgrading slums or rehabilitating degraded settlements, the difficulties
are even greater for a number of reasons: a) these types of intervention
involve specific kinds of technical solutions; b) they are located in
high-risk areas with steep slopes or flood-prone areas; c) inhabitants
remain in the location during construction work; d) executive designs
are almost never available before construction work begins; e) the
numerous agents intervening include financing agents, public bodies and
utility licensees.
These were some of the difficulties we met
with in undertaking the present study. In view of these features and the
scarcity and unsystematic nature of the available data, we took the
approach itemized below:
a) we initially examined previous work on urban
infrastructure costing issues for both formal and informal sector urban
experiences and attempted to identify the variables affecting these
costs;
b) we compiled costs and statistical treatment
for three slum upgrading programs: Guarapiranga in São Paulo,
Favela-Bairro in Rio de Janeiro and Ribeira Azul in Salvador;
c) we compared the three programs between
themselves and in relation to costs studied in item a);
d) we compiled tables showing costs for
different urban infrastructure projects in the informal sector in urban
areas and their typologies.
2. Slum
Upgrading in Brazil
2.1 Approaches to intervention in
slums
Initially, public policies sought to
eradicate slums and relocate residents to housing projects on the
outskirts of the city, and this is still the approach in many areas
(Silva, 1994). This policy proved ineffective over time as relocated
residents often left their new homes and moved back to new slums.
Moreover slum areas have grown considerably, so generalized re-housing
was no longer feasible.
The current approach is to upgrade slum
areas, attempt to keep the community in the same location by building
infrastructure, and seek to regularize property titles. Whether the
community stays on the same site or not will also depend on the risks
involved; relocation may be required when sites are near waste
landfills, under overpasses, or are endangered by mud slides or frequent
floods in riverside areas.
Slum
upgrading projects may be divided into four basic stages following Abiko
(1995).
a) Preliminary study: this stage is crucial
for deciding the technical, physical, and legal feasibility of
implementing an upgrading project in a certain area. This stage will
include initial contacts with residents;
b) Registration: Once an upgrading project is
seen as feasible, residents should be registered. To avoid swelling the
numbers benefiting from upgrading, it is advisable to have the local
population assist with the registration procedure and decide which
families will benefit;
c) Project design: The area selected will be
subdivided to accommodate the largest number of registered families in
the best manner possible, with each family’s lot supplied with water,
electricity, internal thoroughfares and drainage, telephone and sewerage
facilities, and spaces required for utilities to install these systems.
This means designing the project in the way that meets needs most
efficiently;
d) Execution: construction time will depend on
the terrain, the availability of finance and community involvement. Flat
terrain and an easily accessed site will speed construction and
vice-versa. Execution time may vary from several months to years.
Rehabilitating degraded
settlements poses a challenge for specialists and institutions involved,
be they municipal governments, national government agencies, state companies, or
non-government organizations. There have been innumerable cases of
attempts to rehabilitate settlements of this type in Brazil, but little
is known in relation to the outcome of these interventions.
Some sectoral initiatives have been
implemented with solutions specifically designed for slums. Water and
sewerage utilities have used condominium sewerage (Melo, 1994) or 32 mm
HDPE, High Density Polyethylene, which is more malleable than rigid PVC.
Electricity utilities have used smaller metal posts with mains
switchboxes and metering for several households.
However, sector initiatives in slums may
often be consolidating an urban structure that is densely occupied,
unhealthy and inadequate, and at risk geo-technically. Installing water
supplies in a slum means higher sewage volumes that will require
drainage. So when installing piped water in a slum, there has to be a
new sewerage system too. Drains for rainwater must be installed,
otherwise this water will flow into sewers. There has to be garbage
collection to complement water supplies, sewage and rainwater drainage —
in order to avoid solid waste blocking drains and sewers. There must be
a suitable road system for garbage collection to be carried out
properly.
So there is obviously a need to integrate
interdependent initiatives relating to degraded settlement
rehabilitation. This is no easy task since the different technical
specialties involved are associated with institutions that have their
own particular characteristics at different levels of government.
Providing environmental education along with
these initiatives is crucial to the process of rehabilitating degraded
settlements and helping ensure sustainability for upgraded slums.
Experience has shown that rehabilitated urban environments are at risk
of deteriorating again if there is no community involvement in the
process of maintaining a new habitat.
Another extremely important issue is the
cost of these interventions. The state has to respond to a wide range of
demands from society, so public policy makers must pose the question:
what are the costs and benefits of slum upgrading projects? Is upgrading
the most appropriate approach to the slum problem?
Finally, in terms of mobilizing financial
resources, the traditional focus fails to make use of more innovative
financing strategies such as: a) strategies for involving the private
sector through partnerships that do not rely exclusively on public
financial resources; b) clear and transparent subsidy strategies; c)
family-based credit for construction, extensions or improvements to
housing units; d) strategies for recovering costs of investments in
building and infrastructure.
IBAM (2002b) recently studied twelve
municipal slum upgrading or
property-title regularization programs and found that the main sources
of financing were a) municipal
own funds (38.9%), including those from Municipal Housing Funds;
(b) transfers from federal budget (6.3%), including funds under the
Habitar-BID program; c) loans from the official employee severance
fund (local acronym FGTS) and employee assistance fund (local acronym
FAT) (5.4%); d) foreign sources of loans (46.8%), in particular the
Inter-American Development Bank (IDB)
loan to Rio de Janeiro; e) donations from bilateral and multilateral
cooperation agencies (1.2%).
2.2 Characterization of current
slum area interventions
Werna et al.
(2001) reported that slum upgrading
programs led to better quality housing standards in relation to the
structure found in informal settlements. These upgrading programs are
based on specific projects or, in some cases, are part of the process of
general physical planning in urban areas in Brazil (Sallen, 1983, in
Werna et al, 2001)
Three programs were analyzed in this study:
a) the Urban Recovery Program of the Environmental Recovery Program for
the Guarapiranga Basin in São Paulo; b) the Favela-Bairro program in Rio
de Janeiro; c) the Viver Melhor program in Salvador.
2.2.1 The Urban Recovery Program of
the Environmental Recovery Program for the Guarapiranga Basin
The Environmental Recovery Program for the
Guarapiranga Basin, supported by the World Bank, was formulated by a
group of social actors (representatives of the state, municipal
districts and civil society), to tackle the different problems related
to the urban environment of the city of São Paulo. It sought to mitigate
the negative consequences of occupation and use of land in the basin
area, and define and deploy procedures for re-ordering urban occupation.
The Guarapiranga reservoir can hold
approximately 180 million cubic meters of water. The State of São Paulo
Water Supply and Sanitation Company (local acronym SABESP) draws off 12
million cubic meters water per second to meet the needs of approximately
3 million people, corresponding to 20% of the provisioning of the São
Paulo Metropolitan Region. It is the second largest water resource
supplying the Greater São Paulo area.
In 1991, approximately 18% of the population living
around the basin were living in slums.
The portion belonging to the municipality of São Paulo contained more
than 180 clusters of slums. In 1992, informal subdivisions documented in
legal actions in São Paulo's municipal administration in this area
totaled 119.
As one of the subprograms of the
Environmental Recovery Program, the Urban Recovery Subprogram initially
covered slum upgrading activities (25,000 families), adaptation of road
infrastructure and drainage in low-income subdivisions usually located
near slum areas (76,000 families on an area of 10 square kilometers). In
relation to slum upgrading, there were also plans for resettling a small
fraction of the population (3,700 families) to include new housing
projects in well-equipped areas well served by public transport.
In technological terms, the conventional
solutions used were not very flexible bearing in mind the requirements
posed by this type of intervention. An example of this was the fact that
condominium sewerage arrangements were accepted only in very special
situations in relation to access to the sewerage system.
2.2.2 The Favela-Bairro program
The municipality of Rio de Janeiro is the
center of Brazil's second largest metropolitan region. Like most
Brazilian metropolises, the municipality is subject to the consequences
of the phenomena of ‘peripherization’ and informal urban expansion.
As a result of demographic pressure,
aggravated by growing urban poverty and the absence of suitable
alternatives for settlements and housing poor families, the city has a
long history of illegal occupations of public and private land and thus
the multiplication and expansion of informal settlements (IBAM, 2002a).
Most of Rio's slums are on steep hillsides
and subject to collapse, falling stones or rocks, and/or landslides. The
others are in flood-prone areas. According to recent data, more than one
million people are living in slums in Rio.
The Favela-Bairro
program was conceived as an urban policy intervention rather than just a
public initiative to help solve the slum problem in the city of Rio de
Janeiro. In this respect it featured two basic principles: a) upgrading
as the main public policy for slums; b) housing as an urban issue, and
so situated in a broader context.
Note that the Favela-Bairro program is an
integral part of a larger program known as PROAP-RIO, which involves
upgrading of slums and informal and irregular subdivisions.
The Favela-Bairro
program covers 158 slums and benefits 130,000 families or 500,000
people. This amounts to slightly less than half the number of residents
in informal areas of the city. The initial portion of the program was
known as the Low-income Settlements Urbanization Program (local acronym
PROAP I) and covered 90 slums classed as medium scale, i.e. from 500 to
2,500 households.
This program supported by IDB was introduced
in 1994, and aims to upgrade slums, make them into neighborhoods and
promote their inclusion in what is called the 'formal' sector of the
city, after an initial physical and urban planning upgrade. This upgrade
includes physical reorganization, provision of public services,
infrastructure and community equipment.
The infrastructure installed followed the
parameters and technical standards of the utility services licensees
because utility licensees were to take over maintenance and operation
once construction work was executed. In particular the State Water and
Sewage Company (local acronym CEDAE) does not accept technological
alternatives for water supply or sewage drainage systems.
The Favela-Bairro program does not generally
plan on building housing units except in cases of relocation when no
other solution negotiated with families involved is feasible.
In short, the program is characterized by
intervention in terms of provision of urban infrastructure and services.
There is no emphasis on the problem of property-title regularization.
2.2.3 Ribeira Azul program
Salvador has a population of 2,443,107 and
almost all live in the urban area (99.96%), while 875,033 people (35.83%
of the urban population) live in informal settlements. There are 380
slums and 171 informal subdivisions in Salvador, according to the Urban
Development Company of the State of Bahia (local acronym CONDER). Some
208,342 housing units are located in informal settlements corresponding
to 32% of the total number of homes (IBAM, 2002a).
The stated aim of the Ribeira Azul project
is to mitigate poverty in the area of Baía de Todos os Santos. Among its
other aims, priority is posed for actions of a social or environmental
nature.
Preliminary studies were begun in 1992, and
work started in 1995 on 20 slums housing 40,000 families. The lower
income families mostly occupied “palafittes” — that is, shacks built on
stilts above marshy areas.
The project is managed by CONDER, with
participation from the World Bank, Salvador municipal government, and
NGOs such as the Italian AVSI.
Its main components are defining the
external limit of the bays, by landfills and shore side paths used as
dykes to impede the spread of more stilt housing over the mangrove area;
providing basic infrastructure and social equipment for the settlements;
producing more housing units to relocate families affected by the
process of landfilling areas occupied by stilt housing, and financing
housing improvements for surrounding communities.
The project seeks to adopt an integrated
conception promoting environmental, housing, urban planning, and social
and economic improvements, and by working with the participation of the
community and in partnership with social organizations.
There is a varied typology of housing
solutions depending on the needs and financial possibilities of the
families assisted by the project; a) very basic core units to house
families relocated from stilt housing; b)
housing improvements for units located in landfill and consolidated
areas; c) improvement or construction of sanitary units.
In infrastructure terms conventional
solutions are adopted, and the only feature of note was the use of
condominium sewerage as an alternative technology. Basic environmental
education was provided but the community did not take responsibility for
maintaining the sewerage network, and the latter is an important aspect
of this technology.
3.
Cost of Slum Upgrading
This section will look at the issue of slum
upgrading costs from a more conceptual point of view, in the sense of
identifying variables that influence the behavior of these costs.
This will initially mean examining the issue
of infrastructure costs in general, in relation to formal urban areas,
in an attempt to identify the main factors underlying their behavior. On
the basis of this initial examination, we shall then look at the costs
of slum urbanization.
The sources used to analyze both urban
infrastructure costs in general and slum costs were mainly
bibliographical research and the Guarapiranga program in São Paulo.
Information and data from professionals specializing in budgeting and/or
with experience in slum urbanization were incorporated, as were
experiences and reflections noted by the members of team that compiled
this study.
3.1. Factors affecting
infrastructure costs in formal areas
For the initial analysis, a literature
search brought in studies on infrastructure costs from Mascaró (1979 and
1987). Although the amounts of these costs are now outdated, they do
provide an understanding of how infrastructure costs may be affected by
urban planning and physical factors.
The database for these studies consisted of
cost surveys for several Brazilian medium-sized cities in varying
locations. The urban areas considered are in the formal sector, i.e.
they are regularized both technically and legally in terms of urbanism.
The technologies involved in executing the budgets used as the basis for
the analyses are the conventional ones, and therefore follow Brazilian
standards in force at the time.
These studies analyzed the costs of global
supply systems for water, electricity and street lighting, sewerage,
drainage, paving and gas. In view of the scope of the present study, we
analyzed only the costs of infrastructure networks and so excluded
treatment stations, generating stations, etc. The networks covered were
water, sewerage, drainage, paving, electricity, and street lighting.
On the basis of the above studies, we
analyzed cost variations per urbanized area and per house for these
networks, in relation to variations in the following factors:
-
type of layout of the network, basically
depending on the design of the road system and to a lesser extent
the layout of the network itself;
-
size of urbanized greenfield site;
-
shape of field;
-
density of field;
-
slope of field.
We proceed to present a summary of the
influences of the factors mentioned on network costs per urbanized area
and per house.
TABLE 1 - Urban infrastructure networks -
costs per urbanized area and factors influencing them
|
Type of network layout |
Size of field |
Shape of field |
Density of field |
Slope of field |
Water |
A (1) |
B (2) |
(-) |
C |
(-) |
Sewerage |
A (3) |
C |
(-) |
(-) |
B (4) |
Drainage |
(-) |
A |
B (5) |
(-) |
B (6) |
Paving |
A |
(-) |
(-) |
(-) |
A (7) |
Electricity and
lighting |
A |
C |
(-) |
(-) |
(-) |
Source: Adapted from Mascaró (1979
and 1987)
Legend: A - High influence; B -
Medium influence; C - Low influence; (-) insignificant / not detected /
not studied / inconclusive.
Notes: (1) the larger the
extension of the plan, the higher the cost of the network for the same
population.
(2) Costs rise quickly for large fields
(over 400 ha) and moderately for smaller fields.
(3) The smaller the block, the more the
network costs.
(4) Costs rise when a slope is less than 1%
or over 7%.
(5) The longer the basin, the higher the
cost.
(6) Up to a 4% slope, costs decrease; from 4
to 6%. they remain constant; and, at 8% or more, they begin to increase.
(7) Costs tend to rise with the slope, but
they may also - within certain limits - decrease, depending on the
conditions of soil, traffic and the available technological
alternatives.
TABLE 2 - Urban infrastructure networks –
costs per house and factors influencing them
|
|
Size of field |
Shape of field |
Density of field |
Slope of field |
Water |
A |
B |
C |
A |
(-) |
Sewerage |
A |
C |
(-) |
A |
B |
Drainage |
(-) |
A |
B |
A |
B |
Paving |
A |
(-) |
(-) |
A |
A |
Electricity and
lighting |
A |
C |
(-) |
A |
(-) |
Source: Adapted from Mascaró (1979
and 1987)
Legend: A - High influence; B -
Medium influence; C - Low influence; (-) insignificant / not detected /
not studied / inconclusive.
The tables show that the most important
factors affecting costs is type of network layout, and in this respect
road system design – which imposes a certain layout - tends to be the
predominant factor. Alternative layouts for the same road system, when
possible, may affect costs, but are less important. In this respect, the
author notes that the conventional urban "grid" design makes networks
more expensive by requiring greater lengths for the same number of
houses served. "Normal" plans with a hierarchical road layout (main road
and secondary cul-de-sacs feeding into it), are less costly because they
require less extensive networks and involve greater optimization of
capacities such as paving.
Once the urban design is determined, the
other important factor is density. Whatever the network type, the rule
is the greater the density, the lower cost per house unit served.
This is due to the fact that additional
population served in the same area requires smaller increments in the
overall network cost. The cost of a network for 500 inhabitants, for
instance, is not much more than one for 50 inhabitants in the same area.
Following the same author, we also show the
costs breakdown for each network.
TABLE 3 - Composition of cost of
infrastructure networks
Network
|
Incidence on costs (%) |
Water |
4.1 |
Sewerage |
20.2 |
Drainage |
16.5 |
Paving |
47.1 |
Electricity and
lighting |
12.1 |
Total |
100 |
Source: Adapted from Mascaró (1979
and 2003)
As the table shows, the cost of drainage
plus paving accounts for more than 60% of the total costs of
infrastructure networks, and paving alone accounts for almost 50%. In
this respect we once again see the importance of urban design for
infrastructure costs, since it is the design of the road system that
decides the extension and areas of paving, as well as the hierarchical
layout of the latter.
The characteristics of slum areas, which are
typically densely populated with a nested road system plan and smaller
in area relative to a conventional subdivision, might suggest that
network costs per unit served would be less than for a normal urban
area, but this is not the case, as we shall show below.
3.2. Factors affecting
infrastructure costs in formal areas – benchmarks
The costs from which the data shown above
were extracted are in the above mentioned studies by Mascaró. However,
the base date for the latter is 1975 with inflation-adjustment using the
US dollar rate for 1979 and we believe that using the present value on
this basis is not feasible after such a long period.
There are very few specialized publications
or updated studies on this theme in Brazil that could provide updated
benchmarks for infrastructure costs.
One of the few existing sources is derived
from the study conducted by engineers Hélio de Caires and Guilherme
Martins, as part of a method for evaluating urbanizable fields. Costs
obtained using the methodology posed by these authors are
inflation-adjusted and published in specialized magazines; they may be
used as benchmarks in the absence of other costing data obtained from
budgets or executed public works.
The table below shows a summary of the main
infrastructure costs as published in the magazine Construção Mercado
(2003) Note that this methodology uses certain parameters and hypotheses
to simplify the issues and it is also old, so it does not cover
technological innovations or design criteria introduced over recent
years that have probably reduced these costs, such as the use of PEAD
for water networks, the use of simplified sewerage networks, etc
TABLE 4 – Infrastructure cost for urbanizable fields (R$
– May 2003)
|
|
Cost per square meter raw
field |
Cost per 125 square meter
lot |
% |
Water |
2,554.19 |
2.21 |
319.27 |
11 |
Sewerage |
4,767.25 |
4.12 |
595.91 |
20 |
Drainage |
2,398.33 |
2.07 |
299.79 |
10 |
Paving |
11,296.84 |
9.77 |
1,412.11 |
47 |
Electricity and
lighting |
847.70 |
0.76 |
373.15 |
12 |
Total |
21,891.31 |
18.93 |
3,000.23 |
100 |
Source: adapted from the table
"Evaluation of urbanization field-cost" (Construção Mercado, 2003).
Notes:
The original table was altered as follows: average earthmoving taken as
paving cost, as well as curbs and gutters. Project and administrative
fees were eliminated and a rate of 33% included as project (3%) and IDB
(30%). Cost of electricity and lighting was calculated at 12% of total
cost.
One should note that the cost weightings for
networks are relatively similar to those in the tables shown previously.
The biggest differences are for water and electricity, and this may be
explained by the fact that Guilherme Martins' cost included only street
lighting.
Another cost benchmark that may be used as a
basis for infrastructure cost is the incidence of this cost in relation
to the total cost of construction (house plus infrastructure), for
housing projects or condominiums (gated communities).
Data from Cardoso (1993) point to benchmark
urbanization costs for low-income housing projects built in the
Metropolitan Region of São Paulo, with weightings varying from 11 to 28%
of total cost of construction (infrastructure plus houses). Professional
cost estimators work with 15% of cost of infrastructure networks in
relation to total cost of construction (infrastructure plus houses), for
medium or large housing projects (over 300 units).
Taking 15% of infrastructure cost as our
base number, for a low-income standard unit with 50 square meters built
area, and a unit cost of R$ 500 per square meter, the average total cost
of infrastructure networks per unit may be estimated at approximately R$
4,500 on a preliminary basis.
3.3. Factors affecting
infrastructure costs in formal-sector areas
Slum upgrading costs obtained from the
literature and from surveys conducted for this study appear to be quite
high in comparison with the references noted. Averages from the
Guarapiranga program, the main source for this study, are around R$
10,000 or more per family. Therefore we should analyze the
composition of costs and their nature in order to understand variations
in the same way as we approach infrastructure costs in formal-sector
areas This involves an examination, however cursory, of the main
characteristics of slum upgrading work.
3.3.1. General characterization of slum
upgrading work
Slums have specific characteristics making
them quite distinct from formal-sector urban areas since they are
usually located in areas that have not been subdivided, perhaps valley
floors, or steep hillsides, and are not suitable for residential
construction (COBRAPE, 2000). The situation is aggravated by disorderly
and extremely dense occupation hindering work on access roads or water,
sewerage, and drainage networks. In the absence of these networks,
inhabitants may leave effluent and waste on the ground, thus aggravating
soil instability and accentuating sanitary problems.
As we have seen in the initial section of
this study, the first government interventions in these areas in the
1980s sought to mitigate the worst aspects. When possible, basic
services such as piped water and electricity were installed and
sometimes sewerage and drainage and retaining structures were installed
too. However they did plan for interventions of a more structural
nature. Obviously the costs of the interventions executed were quite
low, perhaps even lower than in normal areas.
This study has taken the Guarapiranga
Program executed in the São Paulo Metropolitan Region during the first
half of the 1990s as a benchmark for actions currently being undertaken
in the ambit of slum upgrading programs that are of a different nature.
They aim to consolidate these areas as urban centers that are social and
functionally part of the city, and ensure that certain minimum standards
of environmental and sanitary quality are upheld. Therefore, the
interventions demand a wider scope of construction work, involving a
certain minimum restructuring of the road system, reorganizing and/or
relocating homes when necessary, as well as doing construction work that
also oftentimes involves the area surrounding the slum
The scope of these interventions, in general
terms, and using the Guarapiranga program as a basis, usually includes
the following points:
-
building water supply and sanitary
sewerage networks to serve all housing units following roads used by
pedestrian and vehicle traffic;
-
a road system to facilitate
house-to-house collection of garbage and access to homes;
-
a drainage system, including
straightening and covering over streams when necessary;
-
construction work of a geotechnical
nature, such as retaining structures on hillsides;
-
installing electricity network and
street lighting;
-
providing garbage collection services;
-
treatment of common and collective
spaces compatible with the availability of areas internally or
adjacent to the center;
-
building the least number of new housing
units in different locations, and examining the possibility of
creating new settlement areas and relocating homes within the slum
area itself;
-
building new housing units outside the
slum area, to assist families relocated or re-housed to different
locations;
-
social assistance follow-up for the
benefited communities in order to encourage participation at every
stage in the program.
Although the project incorporated simplified
criteria
and more flexible features in relation to the usual approach, the aim
was for slum networks to meet the same performance standards as those in
normal areas. One example of this in the Guarapiranga program was the
sewerage system, which required a minimum diameter of 200 mm, allowing
condominium networks only in exceptional cases, not exceeding 3% of the
total of the network and having 150mm minimum diameters.
3.3.2. Factors influencing costs
Studies of upgrading slum costs that we
consulted showed that they are more complex in nature than
infrastructure costs in normal areas, and this often impedes a modeling
of their approach.
Rocha et al (2002) studied a number of
upgraded slums in the Guarapiranga Program and detected quite a large
variation in their upgrading costs. They obtained an average of R$
7,962.10 per family (base date August 1995), with a variation of
approximately 30% around the average.
The first was infrastructure costs
(drainage, cleaning or covering rivers or streams, paving, sewage
drains). In the slums analyzed, a linear correlation between these costs
and the area of the road system, modeled following a linear expression.
Therefore by estimating the area of the road system planned, it would be
possible to estimate the cost of this item. What was not so clear was
how the area of the road system would be estimated.
The second is the cost of superstructure
(relocating or re-housing). Relocation involves building homes in the
slum itself, which corresponds to 20% of the cost of superstructure, in
the cases we analyzed. The unit cost for relocation was estimated at R$
12,684.61, with a coefficient of variation of 37.8%. By estimating in
advance, on the basis of the diagnosis, the number of relocations to be
made, the cost could be calculated directly. The weighting for
relocating involving building new units in a different location may be
calculated in the same way, i.e. taking the number of families to be
relocated and multiplying by the unit cost of R$ 25,307.78 (August
1995), an amount that seemed to us be rather high, since if adjusted by
the CUB index
through May 2003, the result would be approximately R$ 46,000.
The third and last cost component is related
to operational activities (executive project, management and maintenance
of construction work, technical consulting services and social
assistance). Data obtained from the slums analyzed showed this cost
being estimated at 30% of the total for infrastructure and
superstructure combined. We thought this rather high as a criterion and
no details of how the index was composed were provided.
Notwithstanding the above points, we applied
this model to the slum (Parque Amélia), which was used as benchmark for
the Guarapiranga program because it seemed closest to the actual costs.
On this basis, our estimated cost was R$ 8,404.50 per family (August
1995), which came very close to the actual cost (R$ 7,603.90 per family,
according to the data obtained).
Another important source we consulted was
Ancona & Lareu (2002), which analyzes a series of 32 slums upgraded as
part of the Guarapiranga program to arrive at a total cost of R$
10,623.94 per family on the base date of December 2000. Of this amount,
R$ 9,701.47 (91.3%) related to infrastructure work (drainage, water,
sewerage, paving), retaining structures and preliminary services (site,
demolition, temporary buildings). The difference was related to the cost
of relocation, which was not analyzed in the study. However, the cost of
R$ 9,701.47 was the average of a range that varied from R$ 4,099.86 to
R$ 30,793.02. The study looked at possible explanations and related
costs to the following factors: slope, number of families, area of slum,
density and duration of construction work. This latter factor had a
major impact on the cost of preliminary services, including monthly cost
items such as site maintenance. However, they did not find a correlation
that could explain variations on the basis of the factors considered.
Note also that costs were inflation-adjusted
for the date December 2000 using the wholesale prices index (IGP-M),
which in our opinion does not accurately reflect variations in this
activity, basically civil engineering and building work. Table 5 shows a
number of price indices and their increases for the period August 1995 -
June 2003; building costs in São Paulo rose between 74.36% and 101.30%,
whereas the IGP-M rose by 135.64%.
Figure 1 shows indexes for the 1994-2003
period.
TABLE 5 – Price indices – August 1995
–
June 2003 (%)
|
Construction Industry |
Economy |
|
SINAPI
SP |
CUB
SP |
ICC
SP |
FIPE
SP |
FIELD
SP |
INCC
BR |
IPCE
SP |
IGP-M |
US$
|
August 1995 - June 2003 |
74.36(1) |
81.18(2) |
88.38(2) |
92.20(2) |
93.07(3) |
94.10(2) |
101.30(2) |
135.64(4) |
206.07(4) |
Notes: (1)
Calculated on the basis of IBGE data;
(2)
Calculated on the basis of data from the magazine Construção Mercado;
(3)
Calculation considering average composition of infrastructure costs,
following the methodology of Fernando Guilherme Martins and values
published in the table "Evaluation of Field-Cost for Urbanization" (Construção
Mercado 2003).
(4)
Calculated on the basis of data from FGV, Fundação Getulio Vargas.
The third study we examined was a report on
slum upgrading compiled by COBRAPE, the management company for the
Guarapiranga program.
Weighted averagecosts
of the program for slum upgrading projects coordinated by PMSP and CDHU
were reportedly R$ 10,623.94 and R$ 10,323.30 respectively (averaging R$
10,473.62) The base date is not explicitly stated in the report but
according to the authors' of the study previously mentioned, which used
the same base date as the report, costs were adjusted using the IGP-M
index through December 2000. The report examines the varying costs for
different slums and poses a number of points to explain this variation.
The first point is that costs of services
were higher than initially estimated. The cost initially planned was US$
1,300 per family, which corresponds to R$ 3,900 per family today,
which is similar to the benchmarks presented previously for urbanization
of normal areas.
FIGURE 1 – Price indices over the period

NB: accumulated variation as of the
base date of August 1995.
Some of the reasons for exceeding the
initial estimate are mentioned. One was that scope was broadened - only
sewerage and paving was planned initially and water was supposed to be
installed by SABESP. Estimates erred in not taking into account the need
for earth moving work to cover distances of over 1 km.
The Report also analyzed variations in the
costs of services and slums that were much higher than average, and
posed the following factors in explain these variations:
a) Paving
The key factors for
costs were the situation of the surrounding area, its topography and the
structure of the center of the slum. Slums located longitudinally along
streams tend to involve higher costs, which is in line with the cost
analyses posed at the beginning of this section. Very uneven terrain and
deficiencies in the urban structure of surrounding area also tend to
raise costs.
b) Water
The main factor is the situation of
surrounding area. Costs increase when there is a need to extend networks
to connect to the slum and decrease when there is a pre-existing supply
network, although partially.
c) Sewerage
Costs related to conditions in the
surrounding area - lack of infrastructure - and larger numbers of
families require more network installation. This contradicts the
analysis posed at the beginning of the section in which higher density
reduced the length of network required per family
d) Drainage
Costs are higher for slums containing small
numbers of families where rivers or stream shave been covered and where
there is no paved road infrastructure around the area.
e) Retaining structures for hillsides
Costs depended on topography; the more
uneven the terrain, the higher the cost. It was also found that amounts
were higher than average in small slums (less than 100 families).
f) Relocating or building new housing units
This item basically depends on the size of
the slum. Those containing less than 100 families generally do not
involve relocations. In medium-sized slums (100 - 300 families) less
than 8.5% need relocating. In large slums (over 300 families) more than
8.5% and as much as 28% may need relocating.
The report also points to difficulties in
construction work due to the characteristics of the slums (high density
and unhealthy settlements, precarious buildings, difficulties in access,
problems with floods and low load-bearing capacity of the soil), that
also drive up costs, although these items were not measured. From this
angle, the relevant points were:
-
difficulties involved in using
equipment, requiring its vertical transport, manual excavation of
ditches and drains;
-
construction work when families remain
in the same location, requiring special tasks and techniques to
ensure residents' safety, such as retaining structures and lowering
the water level to allow excavation;
-
need for continuous revision of
projects, given the extreme mobility of the families, their constant
extensions or new buildings, and the need for temporary lodging to
accommodate families whose houses are affected in the course of the
work or found to be in imminent- risk situations.
The larger the slum, and the more densely it
is occupied, the more these factors seem to be accentuated.
In view of the above data, we may summarize
factors influencing costs in table form, as we did for infrastructure in
formal areas, as follows.
TABLE 6 – Slums upgrading costs per family
and factors affecting them
|
Size of slum (number of
families) |
Topography |
Situation surrounding area |
Layout and location (along
streams) |
Water
|
(-) |
(-) |
A |
(-) |
Sewerage |
A |
(-) |
A |
(-) |
Drainage |
B |
(-) |
A |
A |
Paving |
C |
A |
A |
A |
Retaining
structures |
C |
A |
(-) |
(-) |
New housing units
and relocations |
A |
(-) |
(-) |
(-) |
Legend: A - High influence; B -
Medium influence; C - Low influence; (-) insignificant / not detected /
not studied / inconclusive.
We see that one of the main factors
affecting costs is the size of the slum, i.e. number of families.
Apparently, the more families living in the slum, the higher the cost
per family, although this does not apply to all services. This factor,
we believe, calls for further research, since there is no clear
characterization and the data contradict the points made at the
beginning of the section.
Another key factor is the situation of the
surrounding area, and here there can be no doubts as to its importance.
The more precarious the infrastructure of the surrounding area, or the
more distant the slum is from urbanized areas, the greater the cost
involved and vice-versa
According to the COBRAPE report, costs for
30% of the slums analyzed were higher than the weighted average most of
them were in areas with no infrastructure, so there are no doubts as to
the major influence of this factor.
On a different level we have factors related
to the physical conditions of the slum, its topography (the more uneven
the terrain the greater the cost) its layout and location; slums laid
out longitudinally along streams are more expensive to urbanize.
From the data obtained, it was not possible
to detect a relation between the two main factors, in other words
whether the larger slums tend to be located in worse or better
situations in relation to surroundings. It is possible that the larger
slums are located in or near areas that have better infrastructure,
which would favor their cost in this respect. Small slums may tend to be
located in more distant locations with less urban equipment, which would
make them more expensive to urbanize. On the other hand, large slums
tend to be more densely populated and involve more difficulties for
construction work and more cases requiring relocation. These aspects too
require further research in our opinion.
3.3.3. Cost per service
Based on the factors listed above and costs
incurred, the COBRAPE report classifies slums in two groupings. One
comprises 'average' slums, in which the quantities of services and costs
required correspond to an average frequency interval of 70%. In other
words, this grouping accounts for about 70% of the slums for which
requirements of services and weighted average costs were calculated. The
other set comprises complex slums, for which services requirements and
costs significantly exceeded the weighted average, as shown below.
TABLE 7 – Services (quantified) and
average costs for normal and complex slums
|
Weighted averages – normal
slums |
Weighted averages –
complex slums |
Weighted average costs – normal
slums |
Weighted average costs –
complex slums |
R$ per family - December 2000 |
% |
R$ per family - December 2000 |
% |
Water
meters per family
|
3.40 |
8.83 |
328 |
5.73 |
1,267 |
7.53 |
Sewerage
meters per family |
4.55 |
9.54 |
1,321 |
23.07 |
3,025 |
18.00 |
Drainage
meters per family |
1.56 |
9.20 |
1,528 |
26.69 |
5,064 |
30.13 |
Paving
Sq. meters per family |
13.44 |
39.90 |
1,069 |
18.67 |
3,150 |
18.72 |
Retaining
structures
Sq. meters per family |
6.00 |
19.64 |
508 |
8.87 |
4,311 |
25.62 |
New housing units
and relocation
|
6% |
Over 8.5%(1) |
972 |
16.98 |
(2) |
(2) |
Totals |
|
|
5,726.00 |
100 |
16,817.00 |
100 |
Source: adapted from COBRAPE (2000)
Notes: (1)
estimate
3.3.4. Summary of global costs
The table below shows summaries of global
costs obtained from the studies mentioned above (COBRAPE, 2000) for the
Guarapiranga program. Data are divided for areas covered by PMSP (local
acronym for the municipality of São Paulo) and those under the CDHU
(local acronym for the São Paulo State Housing Company), i.e. the
municipalities of Embu, Embu-Guaçú and Itapecerica da Serra. There is
also an estimate of costs for Guarapiranga based on Rocha et al (2002).
The Ancona & Laureu (2002) data are not included in this summary, since
their overall costs are the same as those in COBRAPE (2000)
Adaptations were made, supplements added
and amounts inflation-adjusted in accordance with the following
criteria.
For Guarapiranga PMSP
and CDHU cost data, obtained from the above-mentioned works (COBRAPE,
2000), data were grouped under three items (infrastructure,
superstructure and social work / casuals / project / administration);
for project and administration we estimated a cost of 8% of the total
cost of the other items. Costs were inflation-adjusted using the CUB-SP
index for December 2000 as base date for the costs shown through June
2003.
For the estimate based on the study of Rocha
et al (2002), the urbanization standard used was located between
alternatives 2 and 3 described therein. Costs were inflation-adjusted
using the CUB-SP index for August 1995 as base date for costs shown
through June 2003.
Note that the totals are quite similar, but
there are significant differences between the three groups in their
incidence.
TABLE 8 – Overall slum upgrading costs
summarized – Guarapiranga program
|
Guarapiranga
PMSP () |
Guarapiranga
CDHU () |
Estimate
Guarapiranga (2) |
R$ |
R$ |
% |
R$ |
R$ |
% |
R$ |
R$ |
% |
Dec 2000 |
June 2003 |
Dec 2000 |
June 2003 |
Aug 1995 |
June 2003 |
Infrastructure (3) |
8,824.24 |
11,849.79 |
76.91 |
7,737.31 |
10,390.19 |
69.40 |
2,351.61 |
3,157.90 |
28.45 |
Superstructure (4) |
1,674.33 |
2,248.40 |
14.59 |
1,661.02 |
2,230.53 |
14.90 |
4,013.18 |
5,389.17 |
48.55 |
Social work / Project/ Administration |
975.28 |
1,309.67 |
8.50 |
1,750.83 |
2,351.13 |
15.70 |
1,902.06 |
2,554.22 |
23.01 |
Total |
11,473.86 |
15,407.86 |
100 |
11,149.16 |
14,971.85 |
100 |
8,269.84 |
11,101.29 |
100 |
Notes and sources: (1)
Adapted from COBRAPE (2000);
(2) Adapted from Rocha et al
(2002);
(3) Infrastructure, water,
sewerage, drainage, retaining works and paving;
(4) Superstructure: housing
units, construction or repair.
3.3.5 Strategies for reducing costs
and improving cost / benefit ratios for interventions
For the identification
of certain key cost factors, we recommend using strategies for reducing
costs and/or improving the cost / benefit ratio for interventions, also
making use of contributions in COBRAPE (2000):
-
undertaking careful diagnostic analysis
covering conditions in the slum and especially the situation of
surrounding area and way in which the slum relates to the latter, in
order to estimate possible costs and on that basis decide the main
lines of the intervention;
-
revaluating the upgrading of small slum
areas distant from the urban fabric (often the case of
water-resource or spring areas), since intervention involves high
costs and encourages irregular occupation in adjacent areas;
-
analyzing as special cases slums located
along streams or in very adverse sites (topography, stability, soil
type, etc), since these factors will require large amounts of
resources;
-
evaluating the possibility of designing
the executive project on the construction site itself, in order to
efficiently match the dynamics of the slums and minimize problems
arising from exceeding initial costs due to modifications. The
executive project would follow the general guidelines and project
criteria defined in the basic project. According to information
obtained by the team, this procedure is being used in Rio de
Janeiro;
-
considering the use of network
technologies using materials that can be transported manually,
minimizing connections and improving sealing properties, such as
plastic systems;
-
including home facilities in the
interventions, using prefabricated or pre-assembled components, such
as installation kits and depending on the location, prefabricated
bathrooms;
-
evaluating the possibility of using
concrete blocks interlocking or paving stone instead of asphalt
paving, since they are suitable for slopes, are more permeable and
may be installed manually;
-
organizing systematic sanitary and
environmental education campaigns (after interventions) to improve
conservation of equipment and discourage further occupation.
Assistance for communities would include - in addition to
urbanization aspects - social involvement, employment and income
generation, etc.
4. Slum Upgrading Cost Data
This section presents summaries of cost data
obtained from slum upgrading programs in three Brazilian state capitals: São
Paulo, Rio de Janeiro and Salvador.
The three were seen as quite positive
experiences, which encouraged further study and research (including
dissertations and thesis), and thus provided data for this study.
4.1 Comparative analysis of three
programs: Guarapiranga, Favela-Bairro and Ribeira Azul
Tables 9 and 10 and Figures 3 and 4 below
summarize bibliographical data from section 3 and data obtained from the
three programs:
TABLE 9
– Slums upgrading
costs – JUNE/2003
Programs |
Guarapiranga/ SP |
Favela-Bairro/ RJ |
Ribeira Azul/ BA |
Sources |
BIBLIOGRAPHY |
CASE-STUDIES |
|
PMSP |
CDHU |
|
Price
indices |
CUB/SP |
CUB/SP |
CUB/SP |
SINAPI/SP |
SINAPI/RJ |
SINAPI/BA |
Services |
R$ |
% |
R$ |
% |
R$ |
% |
R$ |
% |
R$ |
% |
R$ |
% |
INFRASTRUCTURE |
11,849.79 |
76.91 |
10,390.19 |
69.40 |
9,501.73 |
56.84 |
9,252.21 |
57.13 |
6,499.86 |
74.94 |
4,608.40 |
42.34 |
Water |
- |
- |
- |
- |
478.02 |
2.86 |
460.03 |
2.84 |
425.39 |
4.90 |
436.37 |
4.01 |
Sewerage |
- |
- |
- |
- |
2,120.54 |
12.69 |
2,040.76 |
12.60 |
790.68 |
9.12 |
768.62 |
7.06 |
Drainage |
- |
- |
- |
- |
3,051.05 |
18.25 |
2,936.27 |
18.13 |
805.46 |
9.29 |
177.48 |
1.63 |
Paving |
- |
- |
- |
- |
2,382.54 |
14.25 |
2,292.90 |
14.16 |
2,576.59 |
29.71 |
2,981.07 |
27.39 |
Retaining
structures |
- |
- |
- |
- |
919.99 |
5.50 |
885.38 |
5.47 |
945.31 |
10.90 |
- |
- |
Electricity |
- |
- |
- |
- |
389.02 |
2.33 |
472.54 |
2.92 |
- |
- |
122.43 |
1.12 |
Lighting |
- |
- |
- |
- |
38.90 |
0.23 |
47.25 |
0.29 |
188.47 |
2.17 |
122.43 |
1.12 |
Garbage |
- |
- |
- |
- |
- |
- |
- |
- |
40.69 |
0.47 |
- |
- |
Landscape |
- |
- |
- |
- |
121.67 |
0.73 |
117.09 |
0.72 |
727.27 |
8.38 |
- |
- |
SUPERSTRUCTURE |
2,248.40 |
14.59 |
2,230.53 |
14.90 |
4,745.80 |
28.39 |
4,567.26 |
28.20 |
1,358.72 |
15.66 |
5,392.70 |
49.54 |
Construction
and relocation |
- |
- |
- |
- |
2,214.11 |
13.24 |
2,130.82 |
13.16 |
1,358.72 |
15.66 |
5,392.70 |
49.54 |
Preliminary
services |
- |
- |
- |
- |
2,531.69 |
15.14 |
2,436.43 |
15.04 |
- |
- |
- |
- |
Social As., Des.
and adm. |
1,309.67 |
8.50 |
2,351.13 |
15.70 |
2,469.06 |
14.77 |
2,376.17 |
14.67 |
815.14 |
9.40 |
883.43 |
8.12 |
Social
Assistance |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
326.47 |
3.00 |
Design |
- |
- |
- |
- |
589.13 |
3.52 |
566.97 |
3.50 |
815.14 |
9.40 |
230.42 |
2.12 |
Administration |
- |
- |
- |
- |
1,879.93 |
11.25 |
1,809.20 |
11.17 |
- |
- |
326.54 |
3.00 |
TOTAL |
15,407.86 |
100 |
14,971.85 |
100 |
16,716.59 |
100 |
16,195.64 |
100 |
8,673.72 |
100 |
10,884.53 |
100 |
TABLE 10 – Slums infrastructure costs
– JUNE/2003
Programs |
Guarapiranga/ SP |
Favela-Bairro/ RJ |
Ribeira Azul/ BA |
Formal
urbanized lot |
Sources |
BIBLIOGRAPHY |
CASE-STUDIES |
BIBLIOGRAPHY |
|
NORMAL
SLUMS |
COMPLEX
SLUMS |
|
|
Price
indices |
CUB/SP |
CUB/SP |
CUB/SP |
SINAPI/SP |
SINAPI/RJ |
SINAPI/BA |
|
Services |
R$ |
% |
R$ |
% |
R$ |
% |
R$ |
% |
R$ |
% |
R$ |
% |
R$ |
% |
INFRASTRUCTURE |
6,798.28 |
100 |
22,962.70 |
100 |
9,501.73 |
100 |
9,252.21 |
100 |
6,499.86 |
100 |
5,369.30 |
100 |
3,000.23 |
100 |
Water |
439.52 |
6.47 |
1,697.78 |
7.39 |
478.02 |
5.03 |
460.03 |
4.97 |
425.39 |
6.54 |
436.36 |
8.13 |
319.27 |
10.64 |
Sewerage |
1,770.14 |
26.04 |
4,053.50 |
17.65 |
2,120.54 |
22.32 |
2,040.76 |
22.06 |
790.68 |
12.16 |
768.61 |
14.31 |
595.91 |
19.86 |
Drainage |
2,047.52 |
30.12 |
6,785.76 |
29.55 |
3,051.05 |
32.11 |
2,936.27 |
31.74 |
805.46 |
12.39 |
177.07 |
3.30 |
299.79 |
9.99 |
Paving |
1,432.46 |
21.07 |
4,221.00 |
18.38 |
2,382.54 |
25.07 |
2,292.90 |
24.78 |
2,576.59 |
39.64 |
2,981.06 |
55.52 |
1,412.11 |
47.07 |
Retaining structures |
680.72 |
10.01 |
5,776.74 |
25.16 |
919.99 |
9.68 |
885.38 |
9.57 |
945.31 |
14.54 |
- |
- |
- |
- |
Electricity |
389.02 |
5.72 |
389.02 |
1.69 |
389.02 |
4.09 |
472.54 |
5.11 |
- |
- |
503.10 |
9.37 |
109.34 |
3.64 |
Lighting |
38.90 |
0.57 |
38.90 |
0.17 |
38.90 |
0.41 |
47.25 |
0.51 |
188.47 |
2.90 |
503.10 |
9.37 |
263.81 |
8.79 |
Garbage |
- |
- |
- |
- |
- |
- |
- |
- |
40.69 |
0.63 |
- |
- |
- |
- |
Landscape |
- |
- |
- |
- |
121.67 |
1.28 |
117.09 |
1.27 |
727.27 |
11.19 |
- |
- |
- |
- |

FIGURE 3 – Breakdown of
costs of infrastructure services

FIGURE 4 – Breakdown of
infrastructure services
Data obtained from the three programs
prompted the following observations:
-
Total cost for the
Guarapiranga program is similar to that obtained in studies shown in
Section 3;
-
Costs in São Paulo were
highest;
-
Costs were higher in Bahia
than in Rio de Janeiro, and both were lower than São Paulo. The most
costly item in Bahia was superstructure, but the reason for this was not
identified;
-
Paving and retaining
structures in Rio de Janeiro were highly weighted (more than others). In
Bahia, according to our reports, there are few sloping sites, but we
were unable to asses the impact of this fact on costs as a whole;
-
Data for all costs in the
scope of the study were obtained. Electricity network costs for Rio de
Janeiro were not obtained, but Rio was the only city to supply data on
garbage collection;
-
In relation to infrastructure
costs, water supply costs are quite uniform across all programs;
sewerage, drainage and paving costs varied more. Some costs, such as
paving items were lower in São Paulo;
-
No correlations were found for
different typologies and costs, except for São Paulo, where data
obtained correlated infrastructure costs for medium and complex slums,
which are very different.
5. Conclusions and Recommendations
5.1
In
relation to general guidelines for interventions
Slum areas in Brazil have expanded greatly,
and particularly in the last two decades.
The initiatives taken by the government in
relation to this issue have evolved from superficial actions and
measures aimed at minimizing infrastructure deficiencies to broader
interventions seeking to consolidate newly upgraded slum areas as part
of the city. This requires more far-reaching construction work and
involves at least some restructuring of the road system, relocating
and/or re-housing when necessary, and doing construction work that often
affects areas surrounding slums.
The three slum upgrading programs analyzed
in this study were the Guarapiranga program in São Paulo; the
Favela-Bairro program in Rio de Janeiro; and the Ribeira Azul program in
Salvador.
In all these cases, we saw that the scope of
the work is framed within the characteristics described above. The cost
components of the programs include a varied spectrum of actions that may
be grouped under three main headings:
-
infrastructure, water supply and
sewerage networks, road systems, paving and drainage, retaining
walls or structures for hillsides, electricity and street lighting
networks and garbage collection;
-
superstructure: building houses and
relocating in the slum area itself and/or building new housing
units in different areas, treatment of shared areas and collective
equipment;
-
social assistance for the benefited
communities, design and administration.
We found that certain initiatives were not
implemented with the same intensity as others, even though they were in
the guidelines for the programs; this is the case for property-title
regularization and post-occupancy social work assistance.
It was also found the option of providing an
urbanized lot for families relocated from slums has not been used as an
alternative to providing finished housing units.
5.2
In
relation to upgrading costs
The conclusion is that
slum upgrading costs are not similar to formal-sector costs and this
relates to three aspects.
One is that urbanization costs in
formal-sector areas are restricted to infrastructure networks, whereas
for slums the networks constitute a component of overall costs, although
one with a heavy weighting (70 to 75% in São Paulo and Rio de Janeiro
and 50% in Salvador). There are also programs not examined here, such as
the Cingapura program, in which urbanization has still less importance
within the global scope.
Another is that slums have specific
features, so upgrading costs are of a different nature in relation to
formal-sector areas where the cost factors are road system design and
density of occupation. In slums the data obtained for cases in São Paulo
show that the factors weighing most on costs are: firstly, the size of
the slum, in terms of number of families, and the situation of the
surrounding area
— larger slums and those with more precarious
infrastructure are more expensive to upgrade; secondly the physical
conditions of slums (topography, geotechnical conditions and locations
alongside streams or rivers). It was also found that very densely
occupied slums in critical situations physically drive up the costs of
building due to the increased number of construction tasks and services and
the need to use special techniques or manual labor for jobs that could
be done mechanically, such as excavations.
In this respect, the
costs of slum upgrading are higher than those for formal-sector areas.
Based on the theoretical
costs of slum upgrading infrastructure (following the studies we
consulted) for São Paulo's Guarapiranga Program, inflation-adjusted
through June 2003 — approximately R$ 11,000 per family on average, and
the costs of the same program obtained by our own team of R$ 9,502 per
family — we see that these costs are two to three times the theoretical
costs of urbanizing a formal-sector subdivision. The costs obtained as
benchmarks for an urbanized formal-sector lot, as shown in Section 3,
are approximately R$ 3,000 and R$ 4,500.
On the other hand, we
found that the costs of slum upgrading infrastructure amount to
approximately one third the cost of a completed low-income standard
home, which is estimated at around R$ 30,000.
The third characteristic aspect of upgrading
costs is that, factors vary greatly from one slum to another so there is
a wide range of costs across different slums. The analysis made by our
team using data from the Guarapiranga program the weighted average cost
was R$ 16,716.59 per family, but the costs ranged from R$ 7,320.53 to R$
45,898.11, so the coefficient of deviation was 57.07%.
For the other locations analyzed in Rio de
Janeiro and Salvador, although there are some issues in relation to the
data obtained, we saw that the comparable costs are also high, although
less than in São Paulo (lower than São Paulo by 46% and 33%
respectively) and coefficients of deviation between slums are also over
50% in both locations.
We believe that this conclusion poses the
need for planning initiatives to make advance estimates of the magnitude
of costs involved in upgrading the areas in question and using the data
as criterion when deciding slums to be covered.
Other conclusions related to cost analyses
made were:
-
there is a need for updated and in-depth
data that covers upgrading costs, with benchmarks for costing
studies and estimates, as is the case for normal housing projects.
In this respect, the suggestion is to create a national index of
urbanization costs for formal and informal areas, similar to the
SINAPI index for formal housing projects;
-
there is a need for more in-depth
analysis of factors affecting slum upgrading costs since those
identified refer only to slums in São Paulo; they are qualitative
and are not well characterized in some cases; in this respect we
would suggest that related studies use more powerful statistical
instruments to build quantitative models for the behavior of costs
in São Paulo and other locations;
-
we found that inflation-adjusting for
costs varied across and among studies and works consulted and the
agencies that supplied the information. This problem was aggravated
by the fact that certain data — those for São Paulo — date back to
August 1995. In this respect, we suggest conducting studies to
update costs through actual current prices rather than using
indices.
We also concluded that when there is a need
for inflation-adjustment indices, the ones that best reflect variations
in slum upgrading costs are the construction industry indices for each
location. We would emphasize the suggestion of creating an index for
urbanization costs that could also be used as a parameter for
inflation-adjustment.
5.3
In
relation to the data obtained
The data obtained for
São Paulo, Rio de Janeiro and Salvador comprise samples that may be
taken as representative since they refer to some 45% of the slums
covered by the Guarapiranga program in São Paulo, 40% of the population
assisted by the Favela-Bairro program in Rio de Janeiro and 15% of the
families assisted by Salvador's Ribeira Azul program.
Costing data were obtained for all items
falling within the scope of this study, as listed at the beginning of
this section. Note that only Rio de Janeiro provided data for garbage
collection. We therefore suggest that future studies should research the
costs of this item. For items relating to project and administration
costs, no data were obtained from Salvador and there are dubious aspects
in relation to those from Rio de Janeiro. Future research should
undertake more in-depth study of the latter.
Our study of the Guarapiranga program in São
Paulo was much more in-depth than that of the other locations due to its
proximity. Research in São Paulo involved not only collecting numerical
data, but also interviewing professionals who participated in the
program, visiting the locations upgraded, and consulting a relatively
large amount of material made available by the agents responsible. For
the other cities, contacts were made by telephone and e-mail and data
obtained in the same way. Not much information obtained for the physical
characteristics of the slums in these locations, so we were unable to
correlate costs and those characteristics, as we had done for São Paulo,
although only in part. There were issues and lacunae in the data from
Rio de Janeiro and Salvador and they could not be solved in time for
this study. Therefore the data for São Paulo may be generalized to the
Metropolitan Region of São Paulo, but not to other locations. For Rio de
Janeiro and Salvador, the data could be used as an initial benchmark,
but they should not be generalized to these locations unless there is
more in-depth analysis of the latter.
In this respect, we strongly recommended
that this research be continued.
5.4
In
relation to strategies and technologies
Section 3 concludes
with several recommendations relating to strategies and technologies for
minimizing costs or raising the cost-to-benefit ratio of interventions:
-
post-occupation performance and
evaluation for upgraded slums, in the sense of updating project
criteria, technologies and basic guidelines for the interventions,
which could assist in compiling a technical project manual for slum
urbanization;
-
operational and maintenance costs for
equipment and services related to slum upgrading, in the sense of
covering the overall costs of these interventions;
-
monitoring costs of projects using a
cost-tracking spreadsheet and systematic and continuous collection
of life cycle data (conception, execution, maintenance and
post-occupation).
Alex
Abiko
is a Professor of Civil Engineering and former Head of the Department of
Civil Engineering at the Polytechnic School of the University of São
Paulo in Brazil.
Luiz Reynaldo
de Azevedo Cardoso
is a Professor of Civil Engineering at the Polytechnic School of the
University of Sao Paulo in Brazil.
Ricardo Rinaldelli
is an architect and civil engineer teaching at the Polytechnic School of
the University of Sao Paulo in Brazil.
Heitor Cesar Riogi
Haga is a
civil engineer who teaches at the Polytechic School of the University of
Sao Paulo in Brazil.
6. References
Abiko, A.K. 1995.
Introdução a Gestão Habitacional.
São Paulo: EPUSP.
_____.
2003. Quanto custaria urbanizar
uma favela no Brasil? In: A Cidade
da Informalidade, org. Pedro Abramo.
Rio de Janeiro: Livraria Sette Letras.
Ancona, A.L.; Lareu, S.
2002.
Avaliação do programa
Guarapiranga: custos e componentes de infra-estrutura. In: Anais do
Seminário de Avaliação de Projetos: Habitação e Meio Ambiente.
São Paulo:
IPT.
Cardoso, L.R.A. 1993.
Construção habitacional por mutirão:
caracterização, gerenciamento e custos.
Dissertation (Master's degree). São Paulo:
POLI/USP, Civil Engineering Department.
COBRAPE.
2000. Relatório Urbanização de Favelas: gerenciamento da
fase final do programa Guarapiranga e avaliação de seus resultados. São
Paulo: BIRD/COBRAPE, Unidade de Gerenciamento do Programa (UGP).
Construção Mercado.
2003. Tabela Avaliação de Glebas:
custos de infra-estrutura. São Paulo:
PINI, n. 22. Maio.
IBAM. 2002a.
Estudo de Avaliação da
Experiência Brasileira sobre urbanização de Favelas e Regularização
Fundiária: produto 5: Relatórios Finais de Análise.
Rio de
Janeiro: IBAM.
_____.
2002b.
Estudo de Avaliação da Experiência Brasileira sobre
urbanização de Favelas e Regularização Fundiária: produto 6: Relatório
Final: Consolidação das Análises.
Rio de Janeiro: IBAM.
Mascaró, J. 1979.
Custos de infra-estrutura: um ponto de
partida para o desenho econômico urbano. Thesis submitted for position
as professor livre docente).
São Paulo: School of Architecture and
Urbanism, University of São Paulo.,
_____.
1987. Desenho urbano e custos de urbanização.
Brasília: Mhu-Sam.
_____. 2003. Loteamentos Urbanos.
Porto Alegre: Editor L. Mascaro.
Melo, J.C. 1994.
Sistema condominial de esgotos. Brasília:
CEF.
Rocha, R.F.; Carvalho, C.S.; Moretti,
R.S.; Samora, P.R. 2002.
Procedimentos para tomada de decisão em programas de urbanização de
favelas. In: Anais do IX Encontro Nacional de Tecnologia do Ambiente
Construído. Foz do
Iguaçu: Antac.
Silva, A.A. 1994.
Urbanização de favelas: duas experiências em
construção. In: Pólis, n.15.
São Paulo: Pólis.
Werna, E. et al. 2001.
Pluralismo na Habitação.
São Paulo: Annablume.
Return to top |